Rovuma LNG midstream development, Mozambique
21 November 2026Name of the Project
Rovuma LNG midstream development.
Location
Cabo Delgado, Mozambique.
Project Owner/s
The project is led by ExxonMobil Moçambique in the capacity of Area 4 delegated operator.
Area 4 partners, including Mozambique’s State-owned national hydrocarbon company Empresa Nacional de Hidrocarbonetos; State-owned oil and gas corporation China National Petroleum Corporation; Italian multinational energy company Eni; South Korea's State-owned natural gas company Korea Gas Corporation; and XRG, an energy investment subsidiary of Abu Dhabi National Oil Company.
Project Description
The Rovuma LNG project onshore development represents one of the largest private investments in Mozambique’s history. It is expected to include 12 modular liquefaction modules with a total production capacity of 18.6-million tonnes of LNG a year.
Potential Job Creation
Not stated.
Capital Expenditure
Not disclosed.
Planned Start/End Date
A final investment decision (FID) is expected in 2026. Startup is expected in 2031.
Latest Developments
ExxonMobil Moçambique, on behalf of the Area 4 partners, awarded a letter of intent to the SMDC Joint Venture (JV) comprising Saipem, McDermott Energy Solutions, Daewoo Engineering & Construction Co, and China Petroleum Engineering & Construction Corporation in August 2026 for limited engineering and procurement services supporting Phase 1 of the development.
It further awarded an estimated $1.1-billion in pre-investment contracts for critical long-lead upstream equipment supporting the Rovuma LNG Phase 1 development.
The contracts include the engineering, procurement, and manufacturing of subsea production systems, large bore production valves, and offshore line pipe.
Together, these contracts will enable suppliers to start fabricating and manufacturing materials requiring significant quantities, and specialised equipment with extended delivery schedules.
Awarding these contracts before an FID optimises project execution timelines and helps to ensure the availability of critical infrastructure.
Key Contracts, Suppliers and Consultants
SMDC JV comprising Saipem, McDermott Energy Solutions, Daewoo Engineering & Construction Co, and China Petroleum Engineering & Construction Corporation (limited engineering and procurement services supporting Phase 1 of the development); Advanced Technology Valve (engineering, procurement, fabrication, testing and delivery of large-bore production valves); Corinth Pipeworks Pipe Industry Single Member (manufacture, coating, testing, preservation and storage of submerged arc welded line pipe); Sumitomo Corporation of America (manufacture, coating, testing, preservation and storage of seamless line pipe); and Zhejiang Jiuli Hi-Tech Metals Co (manufacture and supply of mechanically lined pipe, induction bends, weld overlay products and associated line pipe systems).
Contact Details for Project Information
ExxonMobil Moçambique communications manager Albertina Palalane, tel +258 84 100 493 or email[email protected].
Related
-
VINCI wins contract to build an LNG tank in Canada
20 November 2026
-
TechnipFMC Awarded Subsea Contracts for ExxonMobil Guyana’s Longtail Project
20 November 2026
-
INPEX Awards McDermott-Baker Hughes Consortium Contract for Ichthys LNG Development
20 November 2026
-
BurnStar Technologies signs licence agreement to power SAF industry with turquoise hydrogen
20 November 2026
-
M2i signs agreement for critical mineral repository in Nevada
20 November 2026
-
Sabey Data Centers signs 10-year Texas solar agreement covering 43.5 MW
19 November 2026


京公网安备
11010802030424号
京ICP备19046776号-2