PV Power seeks minimum LNG power offtake rate of 85%
20 November 2026PV Power is preparing resources for a new investment cycle involving the Quynh Lap and Vung Ang III LNG-fired power projects. However, the company says issues surrounding minimum contracted power output, electricity tariffs and the ability to adjust prices in line with LNG market fluctuations still need to be resolved.
PV Power logo. Photo courtesy of the company.
PV Power (HoSE: POW), a subsidiary of state-owned Petrovietnam, reported positive business results in the first nine months of the year, with consolidated net revenue reaching VND49,406 billion ($1.92 billion) and after-tax profit totalling VND6,899 billion ($267.69 million), equivalent to 614% of its full-year profit target.
The figures were shared by Truong Viet Phuong, PV Power's deputy general director, and Nguyen Dinh Thi, head of the company's planning and economics department, at an analyst meeting themed "A New Beginning – New Achievements", held at Ca Mau 1 and 2 power plants.
PV Power's commercial electricity output reached 19,329 million kWh in the first nine months, equivalent to 89% of its annual target and up 44% from the same period in 2025. Consolidated net revenue achieved 99% of the full-year target, while after-tax profit far exceeded the target approved by shareholders.
The results were driven by high plant availability, proactive fuel supply arrangements and an optimized electricity bidding strategy. In particular, the commercial operation of the Nhon Trach 3 and Nhon Trach 4 power plants in late 2025, coupled with rising electricity demand in 2026, made a positive contribution to business performance.
For the remaining months of the year, the company aims to exceed its 2026 business targets and is striving to achieve total annual electricity output of more than 21.6 billion kWh.
LNG price volatility, power offtake mechanism still face hurdles
One issue drawing investor attention is the operating efficiency of Nhon Trach 3 and Nhon Trach 4 amid sharp fluctuations in international LNG prices.
Nguyen Dinh Thi said the average imported LNG price in the third quarter for the two plants was around $24 per million British thermal units (MMBtu). If LNG prices fluctuate within the range of $25-32 per MMBtu, the plants' electricity production costs could rise to VND5,000-6,200 ($0.24) per kWh. Meanwhile, electricity offer prices for output outside the contracted quantity (QC) range from around VND4,600-5,800 per kWh.
The gap between production costs and electricity offer prices highlights the fuel cost pressures facing LNG-fired power plants, particularly when input gas prices rise. PV Power will therefore work with PV Gas, another subsidiary of Petrovietnam, to seek suitable supply sources based on assessments of LNG market conditions and the power system's dispatch requirements.
In addition to fuel prices, the contracted electricity output mechanism is another key issue for PV Power.
Truong Viet Phuong said the contracted output (QC) for Nhon Trach 3 and Nhon Trach 4 in 2027, under the government's Decree 100/2025/NĐ-CP, must not be lower than 65% of GCO. The company is closely monitoring the 2027 operating plan prepared by the National Power System and Market Operator (NSMO) and submitted to the Ministry of Industry and Trade to obtain more accurate projections of expected output and contracted electricity volumes.
If actual electricity generation (Qm) falls below the contracted output (Qc), the company will receive the difference between the contract price and the market price corresponding to the allocated QC volume, provided the plant is available for operation.
However, for new LNG power projects, PV Power wants the contracted electricity output allocation rate to be at least 85%. Phuong said the company had submitted several proposals to the Ministry of Industry and Trade, but they had yet to be approved.
PV Power's representative also highlighted several major challenges in the electricity pricing mechanism under power purchase agreements (PPAs). In particular, the minimum contracted output mechanism has fallen short of investors' expectations, making it difficult to secure financing for ongoing gas-fired power projects.
In addition, policies supporting investors in developing LNG-fired power plants lack long-term stability, while the prescribed internal rate of return (IRR) used in electricity tariff negotiations remains low. More importantly, there are currently no regulations allowing ceiling bid prices to be flexibly adjusted in response to LNG price fluctuations during actual operations.
These issues directly affect investment efficiency, financing capacity and decisions on participation in new LNG-fired power projects. Improving contractual mechanisms, ensuring guaranteed electricity offtake volumes and establishing fuel price risk-sharing arrangements are considered crucial for projects requiring substantial capital investment.
Preparing two LNG projects, considering capital increase
Alongside the operation of its existing power plants, PV Power is accelerating preparations for investment in two LNG-fired power projects: Quynh Lap in Nghe An province and Vung Ang III in Ha Tinh province.
For the Quynh Lap LNG project, the Nghe An People's Committee approved the investment policy and selected a consortium comprising PV Power, SK Innovation and Nghe An Sugar Co. Ltd. (NASU) as the investor under a decision dated February 12, 2026. The project was granted an investment registration certificate on March 20, 2026.
PV Power deputy general director Truong Viet Phuong (left) and Nguyen Dinh Thi, head of the company's planning and economics department, share information at the seminar. Photo courtesy of PV Power.
Quynh Lap LNG Power JSC was established on September 14, 2026, and held its inaugural general shareholders' meeting on September 18, 2026. The project is currently preparing its feasibility study, environmental impact assessment, specialized technical reports, 1/500-scale detailed planning and front-end engineering design (FEED) for the LNG storage terminal.
PV Power expects to submit the feasibility study for approval in the first quarter of 2027, sign an engineering, procurement and construction (EPC) contract by the end of the first quarter, begin construction in the second quarter of 2027, and bring the project into commercial operation in the fourth quarter of 2029 or in 2030.
Meanwhile, the Vung Ang III LNG power plant project received investment policy approval from the Ha Tinh People's Committee in June 2026, which also approved a consortium comprising PV Power, LILAMA and B.Grimm as the investor.
Dự án đang hoàn thiện hồ sơ nghiên cứu khả thi, trình thẩm định, phê duyệt quy hoạch chi tiết 1/500 và triển khai các công tác chuẩn bị đầu tư khác. PV Power dự kiến trình phê duyệt báo cáo nghiên cứu khả thi trong quý IV/2026-I/2027, ký hợp đồng EPC từ quý I-II/2027, khởi công xây dựng trong quý II-III/2027 và vận hành thương mại vào giai đoạn 2030-2031.
The project is completing its feasibility study documentation for appraisal, seeking approval for its 1/500-scale detailed plan and carrying out other investment preparation work. PV Power expects to submit the feasibility study for approval in the fourth quarter of 2026 or the first quarter of 2027, sign the EPC contract in the first or second quarter of 2027, break ground in the second or third quarter of 2027 and begin commercial operations in 2030-2031.
To implement the projects, PV Power is working with its shareholders to negotiate financial advisory contracts and engaging with domestic and international credit institutions to arrange financing. For the Quynh Lap project, the company has already held discussions with several banks to assess market conditions.
Regarding equity funding, Truong Viet Phuong said PV Power was developing a plan to increase its charter capital during 2027-2030. The move is intended to strengthen the company's financial resources to support its investment program and the development of LNG-fired power projects in the coming years.
Alongside its LNG projects, PV Power is also studying opportunities to expand investment in renewable energy sources, including small hydropower, floating solar power on reservoirs, waste-to-energy and onshore wind power.
With its new investment program, PV Power faces challenges beyond securing funding and ensuring projects are delivered on schedule. The company will also need a more complete electricity pricing framework, clearer contracted output arrangements and reliable fuel supplies. These factors will directly affect the investment efficiency of its next LNG development cycle.
Related
-
Initial results of 3D seismic survey in Amsterdam, Netherlands published
20 November 2026
-
INPEX Awards McDermott-Baker Hughes Consortium Contract for Ichthys LNG Development
20 November 2026
-
Armenia allocates $44,000 for preparatory work on TRIPP project
20 November 2026
-
SOCAR, US-based SLB sign agreement on seismic data processing
20 November 2026
-
Contractors submit technical bids for Bab Gas Cap project
20 November 2026
-
Construction starts on Damascus hotel and mall
20 November 2026


京公网安备
11010802030424号
京ICP备19046776号-2