US$9.17 Billion Sturgeon Data Centre: Meta to Construct Its First AI Facility in Canada

20 November 2026

US$9.17 billion Sturgeon County AI data centre project by Meta is progressing through its early construction phase, with civil and infrastructure works having commenced in June 2026. In a November 10, 2026 response, the Impact Assessment Agency of Canada (IAAC) confirmed that construction activity had substantially begun. This means Meta’s Sturgeon County AI data centre project could no longer be designated for federal impact assessment under the Impact Assessment Act. The agency cited completed and ongoing works. These include site clearing, road construction, underground utilities, fencing and stormwater infrastructure.

Meanwhile, Sturgeon County issued an additional development permit on October 20, 2026. The permit authorized foundation piling for the project’s first data centre building and mechanical yard, with the permit taking effect on November 10.

The milestones also come as Alberta introduces Bill 42. The legislation is proposing tighter regulations for large data centre projects, including minimum residential setbacks and stricter water-use and land-protection requirements. Meta’s project, however, had already substantially commenced physical works before the new legislation was introduced.

$9.17 Billion Sturgeon Data Centre: Meta to Construct Its First Data Centre in Canada

Reported July 9, 2026 – Tech giant Meta announced Wednesday it will construct a massive data center in central Alberta. This data center, known as the Sturgeon Data Centre, will be the company’s first in Canada, as it rapidly builds out computing capacity to support the global AIboom.

Sturgeon Data Centre Capacity

The 1-gigawatt data center will be constructed with the ability to scale up to 1.8 gigawatts. Moreover, it will be located in Sturgeon County. It represents a total investment of C$13 billion, or $9.17 billion, Meta said.

Furthermore, Meta has doubled down on AI, pledging hundreds of billions of dollars to build large AI data centers in the U.S. The Alberta announcement represents the company’s 33rd data center globally.

Meta Sturgeon Data Centre Artistic Impression

Executives made the announcement in Calgary alongside Premier Danielle Smith and other Alberta government officials. They have spent several years courting Silicon Valley tech giants with the aim of spurring a large-scale investment in the oil-and-gas province.

Other Data Center Proposals for Alberta

Alberta’s ⁠technology minister, Nate Glubish, revealed to reporters that there are currently several other gigawatt-scale data center proposals in various stages of development in the province.

“This is the first of its kind, the first of its size, the first of its scale. Also, it won’t be the last,” Glubish said.

Meta, like other tech giants, is facing rapidly expanding power needs. This is as a result of the growth of AI, and Alberta is rich in natural gas which sells at a significant discount to the U.S. benchmark.

The province’s cold climate also makes cooling the massive super-computers and related data center infrastructure more cost-efficient.

Additionally, 20 existing small- to mid-scale data centers in Alberta already pull from the province’s energy grid, which is 60% powered by natural gas. The provincial government is giving new proponents the option to build their own power sources to avoid limits on power capacity.

Funding of Generation and Grid infrastructure for the Data Center

Also, Meta said on Wednesday it will fully fund new generation and grid infrastructure for its Alberta data center, which will consume aboutas much ⁠electricity as 800,000 homes.

Gary Demasi, Meta’s vice president for data center development, said the company will offset that electricity use by investing in clean and renewable energy.

Closed-loop Liquid Cooling System to Reduce Water Use at the Data Center

He also said the data center will use a closed-loop liquid cooling system, meaning its total water use will be less than that of a typical golf course.

Additionally, the company has partnered with Alberta-based Pembina Pipeline (PPL.TO), opens new tab , which announced last week it will go ahead with its Greenlight Electricity Centre, a new natural gas-fired power-generation facility in Sturgeon County which will be in service in ⁠late 2030 and with which Meta has a long-term tolling agreement.

Until that project is operational and for the next decade, Alberta-based power producer Capital Power (CPX.TO), opens new tab will provide 250 megawatts of electricity for the site using its existing natural gas-fired fleet.

Energy Consumption

Also, the project will require approximately 150 million cubic feet per day of natural gas, according to Pembina, helping to create demand for Western ⁠Canadian natural gas producers.

Meta data center constructionThe project will require approximately 150 million cubic feet per day of natural gas.

Moreover, Canada’s government laid out an AI strategy last month that suggested new data center growth would benefit from the country’s clean electricity grid, which is largely powered by renewables and low-emission power sources.

Why Alberta Emerges as a Leading Data Center Development Hub in Canada

But the vast majority of data centers currently in the planning stages in Canada are located in Alberta, where ⁠a reliance on natural gas means the emissions intensity of the province’s electricity grid is almost five times the national average. Also, the region has renewable energy sources that can be utilized to power data centers.

However, environmentalists in Canada were quick to condemn Meta’s plans. Some environmentalists said tech billionaires have no right to the country’s natural resources.

“We need a moratorium on mega-data centers until we have legislated environmental and human rights protections on AI,” said Keith Stewart of Greenpeace.

Meta AI Data Centre in Sturgeon County: Project Factsheet

Project Name: Sturgeon Data Centre

Developer/Owner: Meta Platforms, Inc.

Location: Sturgeon County in Alberta, Canada. The facility is located within Alberta’s Industrial Heartland, approximately 35 kilometers northeast of Edmonton.

Status: Groundbreaking announced July 8, 2026

Project Scale: 2.9 million square feet. It is also Meta’s 33rd data center globally and its first in Canada. The Sturgeon data centre project is also Meta’s largest facility outside the United States.

Total Capital Investment: Over CA$13 billion (approx. US$9.2 billion)

Power Capacity: 1,000 MW

Primary Workload: AI infrastructure and global computing workloads

Target Timeline: Construction underway. Full power-generation integration is targeted for late 2030

Employment: Generates up to 3,000 jobs at peak construction and will support more than 300 permanent, high-skilled operational roles.

Project Team Behind the Meta AI Data Centre in Sturgeon County

Meta: Responsible for site architecture and deploying the advanced AI-optimized hardware. The American tech company will also manage the closed-loop, liquid-cooled technology.

Pembina Pipeline Corporation: Leading energy transportation. Pembina will also be the midstream service provider managing resource supply lines.

Kineticor Asset Management: The primary developer and manager of the project. Kineticor will also serve as the operator of the power generation facility.

Morgan Stanley Infrastructure Partners (MSIP): Global private infrastructure investment platform providing capital and investment oversight.

Capital Power: Executed a long-term Energy Supply Agreement (ESA) to supply 250 MW of backup and baseline capacity from its broader Alberta fleet.

AltaLink: Managing transmission infrastructure and physical grid connections.

Alberta Electric System Operator (AESO): Overseeing regulatory alignment and system reliability to prevent local consumer rate inflation.

PCL Construction & Clark Builders: Leading industrial general contractors tasked with managing the peak workforce of 3,000 tradespeople.

SLB (Schlumberger): Involved in technical infrastructure and civil/energy positioning.

Invest Alberta: Acted as the primary investment attraction agency orchestrating the multi-year deal.

Sturgeon County Council: Municipal authority managing local land zoning (Alberta’s Industrial Heartland) and development permits. Additionally, it will manage the CA$60 million local infrastructure upgrade.

Government of Alberta: Spearheaded by Nate Glubish (Minister of Technology and Innovation) and RJ Sigurdson (Minister of Affordability and Utilities), who established the specific regulatory framework and data center “concierge team” to fast-track the project.